After Action Report Template: What to Include and How to Write One

A ready-to-copy after action report template for project reviews, incidents, and events. Covers what to include, how to run the review, and how Notelyn turns a recording into a finished report.

By Notelyn TeamPublished September 10, 20269 min read

What Is an After Action Report Template?

An after action report template is a fixed structure for reviewing an event, project phase, or incident right after it happens, so the team captures what worked, what didn't, and why while the details are still fresh. The format traces back to the U.S. Army, which developed the after-action review as a way for units to debrief after training or operations without waiting for a formal report weeks later. The same structure now shows up well outside the military: software teams run it after an incident, event planners run it after a conference, nonprofits run it after a fundraiser, and project teams run it at the close of a major phase.

At its core, an after action report answers four questions in order: what was supposed to happen, what actually happened, why there was a gap between the two, and what the team will do differently next time. A template just makes sure those four questions get asked every time, in the same order, instead of the review drifting into a general conversation about how the project felt.

The report itself is usually short, one to two pages for most projects, longer only when an incident caused real damage or cost. Length isn't the goal. The goal is a record that someone can open six months later and understand exactly what happened and what the team decided to do about it, without having to track down the people who were in the room.

An after action report answers four questions, in order: what was supposed to happen, what actually happened, why the gap exists, and what changes next time.

Why Does an After Action Report Template Matter for Teams?

Most teams already talk about what went wrong after a project ends. The conversation happens in a hallway, a Slack thread, or a rushed five minutes at the end of a meeting that's already running long. None of that gets written down in a form anyone can find later, so the same mistake resurfaces on the next project, and the team relearns a lesson it already paid for once.

An after action report template fixes this by forcing two things a casual conversation almost never produces: a written record, and a specific owner for whatever needs to change. The Project Management Institute has repeatedly linked structured post-project reviews to lower repeat-failure rates on future projects, and the mechanism is straightforward. A team that writes down why a delay happened is a team that can check, next time, whether the same warning signs are showing up again.

The template also protects the review from becoming a blame session. When the format asks 'what was supposed to happen' before 'what actually happened,' the conversation starts from the plan, not from a person. That ordering keeps the review focused on the gap between expectation and reality, which is where the useful lessons actually live, rather than on who gets credit or blame for the outcome.

What Should an After Action Report Template Include?

A complete after action report template has seven parts. Smaller reviews can compress a few of these into one section, but skipping any of them tends to produce a report that reads well and changes nothing.

  1. 1

    Objective and scope

    One or two sentences on what the project, event, or operation was meant to accomplish, and what's covered by this specific report. Without this, readers months later have to guess what 'success' would have looked like.

  2. 2

    Timeline of key events

    A short chronological list of what happened and when, especially any point where the plan changed or something unexpected occurred. Keep this factual: dates, decisions, and events, not opinions about them.

  3. 3

    What went well

    Specific practices, decisions, or resources that worked, named clearly enough that someone could repeat them on the next project. 'Communication was good' is not useful. 'Daily 15-minute standups caught the vendor delay three days before it would have blocked the launch' is.

  4. 4

    What didn't go as planned

    The gaps between the objective and the outcome, stated as facts rather than complaints. Each item here should connect to something specific enough to investigate, not a vague sense that things could have gone better.

  5. 5

    Root cause analysis

    For each significant gap, a short explanation of why it happened, not just that it happened. A basic [root cause analysis](https://en.wikipedia.org/wiki/Root_cause_analysis) asks 'why' several times in a row until the answer stops being another symptom and starts being an actual cause.

  6. 6

    Lessons learned and recommendations

    The specific changes the team recommends based on the root causes above. Each lesson should be actionable: a process to change, a check to add, a tool to adopt, not a general statement like 'communicate better.'

  7. 7

    Action items with owners and dates

    Every recommendation that requires someone to actually do something, written with one named owner and a due date. A lesson without an assigned owner is an observation, not a change.

The Complete After Action Report Template

Below is a ready-to-copy after action report template. Paste it into Google Docs, Word, Notion, or a Notelyn note and fill it in during or right after the review.

---

AFTER ACTION REPORT

Project / Event: ___ | Date of Review: ___ | Facilitator: ___ Participants: ___ Report Period Covered: ___

OBJECTIVE AND SCOPE What was this project or event supposed to accomplish? -

TIMELINE OF KEY EVENTS | Date | Event | Notes | |------|-------|-------| | | | |

WHAT WENT WELL - -

WHAT DIDN'T GO AS PLANNED - -

ROOT CAUSE ANALYSIS | Gap / Issue | Why It Happened | Contributing Factors | |-------------|------------------|----------------------| | | | |

LESSONS LEARNED - -

ACTION ITEMS | Recommendation | Owner | Due Date | Status | |-----------------|-------|----------|--------| | | | | | | | | | |

DISTRIBUTION Who should receive this report, and where will it be stored for future reference? -

---

The Root Cause Analysis table sits between the gaps and the lessons on purpose. Jumping straight from 'what went wrong' to 'what we'll do differently' tends to produce fixes aimed at symptoms, since nobody stopped to ask why the gap happened in the first place.

The Distribution line at the bottom matters more than it looks. An after action report that only the people in the review meeting ever see doesn't change anything for the next team that runs a similar project. Name where it lives and who should read it before the next similar project kicks off.

How Do You Conduct an Effective After Action Review?

The template only works if the review that produces it is run well. A rushed ten-minute conversation squeezed into the end of a closing meeting rarely surfaces the real causes behind what went wrong.

An after action review that skips straight to recommendations, before the group agrees on what actually happened and why, tends to fix the wrong thing.
  1. 1

    Schedule it while memory is fresh

    Hold the review within a few days of the project or event ending, ideally within 48 hours for incidents. Details fade fast, and the specific sequence of decisions that led to a problem is exactly what people forget first.

  2. 2

    Invite the people who were actually involved

    Include everyone close enough to the work to know what really happened, not just team leads summarizing secondhand. A frontline participant often remembers the one detail that explains the whole gap.

  3. 3

    Ask the four questions in order

    What was supposed to happen, what actually happened, why the difference exists, and what changes next time. Resist skipping straight to recommendations before the group has agreed on the first three.

  4. 4

    Keep it blame-free

    Frame every gap as a process or plan problem, not a person problem. 'The handoff process didn't account for weekend coverage' gets people talking. 'Sarah dropped the ball' shuts the room down and buries the real cause.

  5. 5

    Assign every action item before the meeting ends

    A recommendation without a named owner and a date rarely survives past the meeting. Read the action items list back before anyone leaves, the same way you would confirm tasks at the end of a status meeting.

How Does Notelyn Turn a Recording into an After Action Report?

Writing a good after action report while also facilitating the review is hard. Whoever is running the discussion is usually too busy managing the room to also capture root causes and action items accurately. Notelyn removes that trade-off by generating a structured report from a recording of the review itself.

  1. 1

    Record the review or upload the file

    Use Notelyn's built-in recorder during the after action review, or upload a file afterward (MP3, MP4, WAV, M4A). You can also paste a link to a recorded Zoom, Google Meet, or Teams session, no bot needs to join the live call.

  2. 2

    Check the automatic transcript

    Notelyn generates a timestamped, speaker-labeled transcript of the review. A quick pass to fix project names or technical terms takes a couple of minutes and improves everything generated from it afterward.

  3. 3

    Generate the AI summary

    Notelyn separates the discussion into what went well, what didn't, and proposed lessons, picking up on the same language a facilitator listens for: 'the delay happened because,' 'next time we should,' 'I'll own that fix.'

  4. 4

    Produce Meeting Minutes with owners and dates filled in

    The Meeting Minutes output organizes participants, decisions, and action items into one document, with each recommendation tied to a name. Fill in any due date the recording left vague before sharing the report out.

  5. 5

    Ask the AI Q&A assistant to confirm root causes

    Questions like 'why did the launch slip' or 'who owns the vendor process fix' get answered directly from the transcript, without rereading the entire recording to check what was actually said.

Getting Started with Your After Action Report Template

An after action report template doesn't need to be complicated to be useful. Use the seven sections above, ask the four core questions in order, and assign every recommendation to a named owner with a date before the review ends. Those habits are what turn a debrief from a conversation people forget into a document the next project actually reads.

Start with the copyable template in this guide on the next project review, incident debrief, or event wrap-up. If your team already records these sessions, or wants to start, Notelyn can generate a complete after action report from the audio automatically, with what went well, what didn't, root causes, and action items already organized. For the habits that keep those action items from stalling out after the report is written, see our guide on meeting notes with action items, and for turning any recap into next steps, see meeting follow up.